Skip to main content

Aubrey, Texas - City Development Fees

Aubrey | City | Denton County | Dallas-Fort Worth-Arlington MSA (US-377 corridor north of Denton)

Aubrey is a fast-growing home-rule city in Denton County along the US-377 corridor north of Denton, in the north Dallas-Fort Worth metroplex. The City operates its own water and wastewater utility and maintains a Capital Improvements Advisory Committee. It administers water and wastewater impact fees per living unit equivalent plus roadway impact fees by service area; zoning, plat, and site plan application fees; and one-time water and sewer connection and meter fees, all through its consolidated Appendix A Fee Schedule in the Code of Ordinances. The figures below are drawn from that codified Fee Schedule, updated by Ordinance 948-26 (adopted 2/26/2026; code current-through 2026-05-28). As noted in the coverage notes, the fee schedule is published on a portal-gated code service; the currency caveat below applies. Verify current amounts with the City of Aubrey before relying on them.

On this page
  1. Fee summary
  2. Impact fees
  3. Zoning and plat application fees
  4. Water and sewer tap fees
  5. Coverage notes
  6. Fee authorities
  7. Sources

Fee Summary

Fee Type Status Top-Line Figure Effective Date
Impact Fees (water and wastewater per living unit equivalent; roadway by service area) Confirmed Water $5,820.00 per LUE; wastewater $10,586.00 per LUE (SF total $16,406.00); roadway SF-detached Service Area 1 $2,935.62 Codified Appendix A (Ordinance 948-26, adopted 2/26/2026)
Zoning and Plat Application Fees (zoning, SUP, plat, site plan, variance) Confirmed Zoning change $700.00; site plan $500.00; SUP $500.00; variance $350.00 Codified Appendix A (Ordinance 948-26, adopted 2/26/2026)
Utility Tap / Meter Fees (municipal water and wastewater utility) Confirmed Water tap 3/4" $1,200.00; sewer tap 4" $1,700.00; water meter 3/4" $350.00 Codified Appendix A (Ordinance 948-26, adopted 2/26/2026)
Special District Fees Not administered No special-district fee line item appears in the codified Appendix A Fee Schedule -
Proffers Not applicable Texas has no cash proffer regime; exactions run through TLGC Ch. 212 and Ch. 395 -

Impact Fees

Source: City of Aubrey Code of Ordinances, Appendix A - Fee Schedule sec. A7.001. Aubrey operates its own water and wastewater utility and levies water and wastewater impact fees per living unit equivalent (LUE) under Texas Local Government Code Chapter 395, collected at 50 percent of the maximum. The City also administers a roadway impact fee assessed by service area and ITE land use.

Impact FeeAmount
Water impact fee per LUE (collected at 50% of max)$5,820.00
Wastewater impact fee per LUE (collected at 50% of max)$10,586.00
Single-family residential utility impact total (simple meter <=1": water $5,820 + wastewater $10,586)$16,406.00
Roadway impact fee - single-family detached, Service Area 1$2,935.62
Roadway impact fee - single-family detached, Service Area 2$4,177.83
Roadway impact fee - office building, Service Area 1 / 2$4,497.12 / $6,400.08
Roadway impact fee - shopping center, Service Area 1 / 2$7,536.84 / $10,726.06

A living unit equivalent represents the demand of one standard connection; larger meters and higher-demand uses are assessed as multiple living unit equivalents. The roadway impact fee is assessed from a service-area and land-use table, so amounts vary by ITE land use and by Service Area 1 or Service Area 2; the single-family detached, office, and shopping center rows above are representative entries. These capital-recovery impact fees are distinct from the utility's own connection and meter charges below.

Zoning and Plat Application Fees

Source: City of Aubrey Code of Ordinances, Appendix A - Fee Schedule sec. A8.001 (Planning and zoning fees / Development Fees). The figures below are captured verbatim from the codified fee schedule and corroborated by the City's application forms.

Application TypeFee
Zoning change and review fee$700.00 (+ $10/letter, $20/certified)
Zoning verification letter$50.00
Site plan application$500.00
Specific use permit (SUP) application$500.00
Variance application$350.00 (+ $10/lot + $10/certified letter; non-refundable)
Preliminary plat - SF residential$550.00 + $20/lot (commercial/MF $600 + $25/acre)
Final plat - SF residential$650.00 + $20/lot (commercial/MF $700 + $25/acre)
Minor plat / replat / amended plat$500.00 / $550-$600 / $350.00

Authority: City of Aubrey Development Services. The variance application fee of $350.00 in the current codified schedule is authoritative; a standalone variance application form still showing $300.00 predates Ordinance 948-26.

Water and Sewer Tap Fees

Source: City of Aubrey Code of Ordinances, Appendix A - Fee Schedule sec. A7.002 and sec. A7.003. Aubrey operates its own water and wastewater utility. These one-time connection (tapping) and meter charges are the utility's own connection costs and are distinct from the impact fees above.

ConnectionFee
Water connection/tapping fee - 3/4"$1,200.00
Water connection/tapping fee - 1"$1,300.00
Water connection/tapping fee - 2"$1,800.00
Water meter fee - 3/4"$350.00
Water meter fee - 1"$480.00
Sewer connection/tapping fee - 4"$1,700.00
Sewer connection/tapping fee - 6"$1,850.00

Authority: City of Aubrey Public Works Utility. Larger water connections run to 6 inch and larger sewer connections run to 10 inch in the codified schedule; miscellaneous charges (connection fee, reconnect, meter box, endpoint) also apply. Utility service deposits are not development fees and are excluded here.

Coverage Notes - What This Page Does Not Cover

Per ZoneFee's Partial-Verified Publication Standard, the items below were either not itemized in full on this page or are not administered by this jurisdiction. They are disclosed here rather than estimated, paraphrased from a non-official source, or omitted silently. These items remain under limited-coverage review until any remaining gaps are closed from official sources.

Currency caveat

All three confirmed fee families derive from the codified Appendix A Fee Schedule in the City's Code of Ordinances, published on a portal-gated code service that renders through a browser challenge. The most recent fee-schedule amendment is Ordinance 948-26, adopted 2/26/2026, with the code current-through 2026-05-28. The zoning and plat amounts are additionally corroborated by the City's byte-stable application forms, which were re-confirmed present at review. Because the fee schedule sits behind a portal that can update without a new document link, this page carries a standing currency caveat. Confirm the current amounts directly with the City before relying on them.

Roadway impact fee - service-area schedule

The roadway impact fee is assessed from a service-area and land-use table; the amounts above are representative single-family detached, office, and shopping center entries for Service Area 1 and Service Area 2. Developers assessing the roadway impact fee for a specific ITE land use should confirm the applicable service area and per-unit amount directly with the City.

Special district fees

No special-district (municipal utility district, public improvement district, or municipal development district) dollar fee line item appears in the codified Appendix A Fee Schedule. Aubrey has a Municipal Development District but publishes no development fee schedule for it. In Texas, public improvement district formation costs under Local Government Code Chapter 372 and municipal utility district formation costs under Water Code Chapter 54 are recovered through the district itself or a negotiated development agreement, not through a standardized per-application city fee. Closed-search outcome: this fee family is not administered by this jurisdiction.

Proffers

Cash proffers are a Virginia statutory instrument under Virginia Code Section 15.2-2303.4 with no Texas counterpart. Texas exactions run through Local Government Code Chapter 212 (subdivision and development) and Chapter 395 (impact fees). Closed-search outcome: this fee family does not apply to this jurisdiction.

Fee Authorities

Authority Fee Types Official Website
City of Aubrey Development Services Zoning, specific use permit, variance, plat, and site plan application fees aubreytx.gov
City of Aubrey Public Works Utility Water and wastewater impact fees and roadway impact fees under Texas Local Government Code Chapter 395; water and sewer connection and meter fees aubreytx.gov

Aubrey sits on the US-377 corridor north of Denton, the Denton County seat, in the Dallas-Fort Worth metroplex. See also the impact fees guide for how Texas Local Government Code Chapter 395 works.

Sources

Document Agency Accessed
Code of Ordinances, Appendix A - Fee Schedule sec. A7.001 (utility/impact/tap) and sec. A8.001 (planning/zoning); Ordinance 948-26 adopted 2/26/2026 City of Aubrey Code of Ordinances (ecode360, General Code, custId AU6231) 2026-08-11
City of Aubrey Plat Application (Application Review Fee $500; plat fee table matching codified Appendix A) City of Aubrey (Plat Application) 2026-08-11
City of Aubrey Site Plan Application (Site Plan Fee $500) City of Aubrey (Site Plan Application) 2026-08-11

Last verified by ZoneFee: 2026-08-11. Fee schedules are subject to change. Verify current rates directly with the City of Aubrey (Development Services and Public Works Utility) before relying on this data for any financial decision.

This page reflects fee data sourced from the City of Aubrey codified Appendix A Fee Schedule in the Code of Ordinances (Ordinance 948-26, adopted 2/26/2026), corroborated by the City's byte-stable plat and site plan application forms. ZoneFee does not guarantee that fee amounts are current at the time you read this page. Fee schedules change. As noted above, this page carries a currency caveat because the schedule is published on a portal-gated code service that can update without a new document link; the roadway impact fee is assessed from a service-area and land-use table; Texas has no cash proffer regime; and no special-district fee appears in the schedule. Verify all current rates directly with the City of Aubrey before relying on this data for land acquisition, project budgeting, or any financial decision. This page is for research and due-diligence reference only - it is not legal or financial advice.