Celina, Texas - City Development Fees

City of Celina | Collin County | North Texas | Dallas-Fort Worth-Arlington MSA

Celina is an incorporated home rule city primarily in Collin County, straddling into Denton County in its western portions, subject to Texas Local Government Code Chapter 395 requirements for development fee assessment. The City of Celina administers roadway, water, and wastewater impact fees through its Engineering Department, and zoning, plat, site plan, and building permit application fees through Development Services per the City of Celina Master Fee Chart (updated November 11, 2025). Celina is one of the fastest-growing cities in the United States, with heavy master-planned-community development north of Prosper.

On this page
  1. Fee summary
  2. Impact fees
  3. Zoning, plat, and building permit fees
  4. Utility tap fees
  5. Special districts
  6. Fee authorities
  7. Sources

Fee Summary

Fee Type Status Top-Line Figure Effective Date
Roadway Impact Fee (Single Family Detached) Confirmed Service-area-dependent (2025 RIF study; example ~$14,000 per unit, Service Area 4) Mar. 12, 2025 (2025 RIF study)
Water Impact Fee Confirmed Per meter: 1-inch $6,815 to 8-inch $272,600 Mar. 12, 2025 (2025 W/WW study)
Wastewater Impact Fee Confirmed Per meter: 1-inch $10,233 to 8-inch $409,320 Mar. 12, 2025 (2025 W/WW study)
Zoning / Planning Application Fees Confirmed Zoning Change / PD $750; SUP $500; Site Plan $750; plats $400 to $500 + $15/lot Nov. 11, 2025 (Master Fee Chart)
Building Permit Fees Confirmed New 1-2 family $1.12/sq ft under roof + $50 application + $425 plan review Nov. 11, 2025 (Master Fee Chart)
Utility Tap / Connection Fees Not a separate fee Developer water/sewer capital is the impact fee; $200 refundable deposit only -
Proffers Not applicable Texas does not use proffer agreements -
Special District Fees Per-district assessment PID assessments are set per district, not a standing city fee -

Impact Fees

Celina assesses roadway, water, and wastewater impact fees under Texas Local Government Code Chapter 395. The current amounts come from the City's 2025 impact fee studies (Roadway Impact Fee Study, January 2025; Water and Wastewater Impact Fee Report, July 2025) and apply to plats approved on or after March 12, 2025. The applicant-collected fee is computed in the official 2025 Celina Impact Fee Estimator (worksheet last updated August 20, 2025). Administered by: City of Celina Engineering.

Water and Wastewater Impact Fees (2025 study; per meter size)

Meter Size (Living Unit Equivalents) Water Wastewater
1-inch Displacement (1.0 LUE)$6,815$10,233
1.5-inch Turbine (2.5 LUE)$17,037$25,582
2-inch Compound (4.0 LUE)$27,260$40,932
4-inch Compound (12.5 LUE)$85,187$127,912
8-inch Compound (40 LUE)$272,600$409,320

A standard single-family home on a 1-inch displacement meter pays $6,815 water plus $10,233 wastewater, a combined $17,048 in utility impact fees. Amounts scale with meter size per living unit equivalent. Source: City of Celina 2025 Water and Wastewater Impact Fee Report and 2025 Celina Impact Fee Estimator.

Roadway Impact Fees (2025 RIF Study; by roadway service area)

Administered by: City of Celina Engineering. The roadway impact fee is assessed per development unit by roadway service area, using the PM-peak trip rate multiplied by trip length multiplied by the adopted cost per vehicle-mile (Single-Family Detached: PM trip rate 0.94, trip length 4.895 miles). Because the fee varies by service area, a single-family detached home does not carry a single flat citywide amount; the example worksheet for Service Area 4 yields approximately $14,000 per dwelling unit. The full ITE land-use roadway table is published in the 2025 Celina Impact Fee Estimator. Confirm the applicable service area and per-unit rate for a specific plat with City of Celina Engineering before relying on any amount.

Zoning, Plat, and Building Permit Fees

Planning, zoning, plat, site plan, building permit, and engineering fees are published in the City of Celina Master Fee Chart (DocumentCenter View 8089, document header "UPDATED NOVEMBER 11, 2025"). Administered by: City of Celina Development Services / Planning.

Planning and Zoning Application Fees

Application Type Fee
Annexation / Planned Development / Zoning Change$750
Specific Use Permit$500
Site Plan Review$750
Application Fee$300
Plat Processing Fee$300
Minor / Amending / Conveyance Plat$400
Preliminary / Replat / Final Plat$500 + $15/lot
Variance (Board of Adjustment) / Historic Preservation$300
Zoning Verification Letter$200
Zoning Signage$350
Alley / Right-of-Way Abandonment$300
Development Agreement (Minor / Standard / Major)$1,000 / $5,000 / $12,000
Downtown Parking (in lieu)$3,000 per space

Building Permit and Engineering Fees

Fee Type Amount
New 1-2 Family - Application$50
New 1-2 Family - Plan Review$425 (+$200 each additional after 2nd)
New 1-2 Family - Building Permit$1.12 per sq ft under roof
Certificate of Occupancy$75
Commercial Building PermitGross area x ICC sq ft cost x 0.0075
Multi-Family Building Permit$0.90 per sq ft under roof
Parkland Dedication1 acre per 50 lots (or $3/sq ft)
Park Improvement$1,500 per unit
Civil (Engineering) Permit - Residential$601 per lot
Civil Permit - Non-Residential$23,358 per acre
Civil Permit - Multi-Family$8,037 per connection
Site Development Admin Fee$2,476

Source: City of Celina Master Fee Chart (DocumentCenter View 8089), document header updated November 11, 2025.

Water and Sewer Tap / Connection Fees

Celina does not publish a separate one-time developer water or sewer tap fee schedule. The City's developer-side water and wastewater capital recovery is administered as the Water and Wastewater Impact Fees (per meter size) shown in the Impact Fees section above. The Master Fee Chart Utility Rates and Charges section publishes only ongoing monthly water and sewer service rates plus a refundable Water Deposit ($200 per residential living unit), and the Building Permit section cross-references "Capital Recovery Fees: If/When applicable" and "Impact Fees: See Impact Fee chart." Recurring monthly retail water and sewer service rates are out of ZoneFee scope, since recurring operating costs are not development fees. Confirm any project-specific connection cost with City of Celina Development Services or Engineering.

Special Districts and County Overlap

Celina is primarily within Collin County (city hall in Collin County) and straddles into Denton County in its western portions, the same Collin/Denton-line pattern as neighboring Prosper and Frisco. The county straddle has not been verified from official city-limits GIS by ZoneFee.

Celina makes heavy use of Public Improvement Districts (PIDs) to finance master-planned-community infrastructure. PID assessments are per-district service-and-assessment plans - property-specific bond-repayment assessments fixed at district creation - not a standing city-wide development fee, and they are not enumerated as a fee line in the Master Fee Chart. The Master Fee Chart's "District Decertification" fee ($1,750 per acre or $2,500 per meter) is a decertification processing charge, not a developer special-district creation or assessment fee. Consistent with the Prosper and Frisco precedent, ZoneFee treats PID assessments as separate from standing development fees. Developers operating within a specifically-named PID should confirm applicable assessments with the district's service and assessment plan or the City of Celina.

Fee Authorities

Authority Fee Types Official Website
City of Celina Development Services / Planning Zoning, planned development, specific use permit, site plan, plat, and building permit fees (Master Fee Chart) celina-tx.gov/478/Development-Services
City of Celina Engineering - Impact Fees Roadway, water, and wastewater impact fees (Texas Local Government Code Chapter 395; 2025 studies) celina-tx.gov/1444/Impact-Fees

Sources

Last verified by ZoneFee: 2026-06-28. Fee schedules are subject to change. Verify current rates directly with the City of Celina before relying on this data for any financial decision.

This page reflects fee data sourced from official City of Celina documents as of the last-verified date above. ZoneFee does not guarantee that fee amounts are current at the time you read this page. Fee schedules change. Roadway, water, and wastewater impact fees are assessed under Texas Local Government Code Chapter 395 per the City's 2025 impact fee studies and apply to plats approved on or after March 12, 2025; the roadway single-family amount is service-area-dependent and the ~$14,000 figure is an example worksheet output for Service Area 4, not a flat citywide amount. Planning, zoning, plat, site plan, building permit, and engineering fees are from the City of Celina Master Fee Chart (updated November 11, 2025). Celina does not publish a separate developer water or sewer tap fee schedule; developer water and wastewater capital recovery is the impact fee above, plus a $200 refundable water deposit. Recurring monthly retail water and sewer service rates are out of ZoneFee scope. Public Improvement District (PID) assessments are set per district in each district's service and assessment plan and are not a standing city development fee. Texas does not use Virginia-style cash proffers. Verify all current rates with City of Celina Development Services or Engineering before relying on this data for land acquisition, project budgeting, or any financial decision. This page is for research and due diligence reference only - it is not legal or financial advice.